Hydro Update April 2015

This is an update from Marylena Stea, Public Affairs for Toronto Hydro ” Our contractor, Technicore, has finished excavating the tunnel and lining it with concrete, which was the most invasive part of the project. The next step is to rebuild components of the existing junction on Bayview Heights Drive. We expect the junction work to take … Continue reading Hydro Update April 2015